Project Management Plan
From REBAG
Contents |
Description
This document describes the activities that are planned from January until December 2006. The main goal for this year is twofold.
- First, conceptualize the project, and write adequate documentation so that other people can learn more on Rebag.
- Second, deliver a first version of Rebag Ware, the software demonstrator to support Rebag.
Documentation
Documentation on Reputation-Based governance - Documentation on Rebag Ware.
Organization
The non-software activities will be carried out by Lucio Picci. The production of Rebag Ware is outsourced to E-Learning Lab. The specifications of Rebag Ware will be decided jointly by LP and Tek Tank.
Planning
The project is split into .. main activities, or "Work packages" (WP).
WP 1 - Conceptualization - Manager: Lucio Picci
Layout the conceptual issues, to be used for: a) Planning of Rebag Ware b) writing documents and papers
Deliverables:
- General conceptual scheme (an input for WP 3). Due date: 31 January 2006 (first draft, to be refined until 31 Dec.)
- Documentation:
- Reputation-Based Governance: a Primer, First draft. Due date: 28 February 2006 (a new draft isin progress. May 5)
- Reputation-Based Governance of Public Works, First draft. Due date: April 30 2006 (done)
- Reputation-Based Governance: a Primer, Third draft. Due date: 15 December 2006
WP 2 - Communication - Manager: Lucio Picci
Use output of WP 1 to tell other people about the project ant its progresses.
Deliverables:
- Meetings
- Conferences
- Merida, Yucatan, Mexico, March (cancelled by the organizers)
- Rome, September
WP 3 - Rebag Ware - Manager: Cristiano Leoni
Build a sowftare demonstrator to support Reputation-Based Governance
Deliverables:
- The software Rebag Ware
WP 4 - Management - Manager: Lucio Picci
This is a dummy Work Package for general management activities.
Budget
The budget for 2006, as of 5 Jan 2006, is:
- One full time equivalent programmer
- Around 3 months of LP
Supplies
The facilities of E-Learning Lab and of the University of Bologna will be used free of charge (hardware, Internet connectivity).
Risks
The two main goals of the project (conceptualization and software production) have a one way interdependence: if the conceptualization fails, Rebag Ware fails. However, the opposite is not necessarily true. So the biggest risk is a relative failure in developing the model.
List of risks:
- Failure in developing the model
Probability: 0.3, Impact: 10 (from 0 to 10)
- Failure in devoloping a prototype of Rebag Ware (conditional on a good model being available)
Probability: 0.2, Impact: 5 (from 0 to 10)
- Failure in communicating Rebag
Probability: 0.5, Impact: 8 (from 0 to 10)
- Failure in getting other people to join in the effort
Probability: 0.7, Impact: 7 (from 0 to 10) (It will probably take some time, the effort must be persistent)